Vietnam SSIT international container terminal project contract amount of $47 million 870 thousand, for the high pile wharf. Terminal is divided into the main container terminal and the barge terminal two functional areas, the main pier of a total of 67 rows, length of 600 meters, width of 60 meters, there are 80 thousand two ton berths, barge terminal 280 meters long, 22 meters wide. The terminal through the 4 bridge and the rear yard connection. The project started in January 21, 2010, completed in early January 2012, the transfer of construction in February 16th, 6 months ahead of schedule in advance of the contract.